LightMake L4: delivery of the Kickstarter printer slips to late January 2027
Several defects showed up during the trial production run. About 15 testers get a unit in late December, with backers following in late January.
Backers of the LightMake L4 colour printer will have to wait longer. The L4 has four toolheads and a linear motor drive and was funded on Kickstarter. In a production update dated 13 November, the founder writes that several defects showed up during the trial production run.
What was wrong
- The housing colour did not meet the specification.
- A flaw in the injection mould for the power supply box leaves surface defects.
- The USB-C connection of the folding screen could loosen over time, so an extra retaining part is being added.
- The nozzle wiper did not clean the nozzle completely and has been redesigned.
- A test print showed layer lines, so print parameters are being tuned.
- Assembly workers are still learning the process.
None of these is serious, the founder writes, but he does not want to ship machines like this.
New schedule
- Late December 2026: about 15 testers receive a unit
- Early January 2027: fixes based on tester feedback
- Late January 2027: delivery to backers in order sequence
According to a notice on the page, LightMake is extending the warranty to 24 months.